Client Alerts  - Energy and Renewables Jun 16, 2020

NYS Agencies Propose Reforms to Achieve Energy and Climate Mandates

New York State Agencies Propose Sweeping Reforms to Achieve Energy and Climate Mandates

The Department of Public Service Staff (“DPS Staff”) of the New York State Public Service Commission (“Commission”) and the New York State Energy Research and Development Authority (NYSERDA) are moving at breakneck speed to position New York State as a global leader in clean technology and climate policy. In just over six months since the Climate Leadership and Community Protection Act (CLCPA) went into effect, DPS Staff and NYSERDA published a groundbreaking whitepaper setting forth a proposed framework and regulatory pathway to decarbonize New York State’s power grid (“CLCPA White Paper”).

The CLCPA White Paper is the first step in a process that will ultimately lead to the Commission establishing a CLCPA-mandated “program” by June 30, 2021, which will require 70% of electric load to be served by renewable energy by 2030 (“70×30 Target”) and achieving a zero-carbon emissions Statewide electric grid by 2040 (“2040 Zero-Emissions Target”). Once the “program” is established, Public Service Law Section 66-p requires the Commission to make appropriate adjustments every two years thereafter to ensure continued progress toward the statutory requirements.

The CLCPA White Paper is densely packed with policy proposals and conceptual frameworks that shed light on the manner in which those ambitious targets might be achieved. At its core, the CLCPA White Paper proposes to rely on the existing (but modified) Clean Energy Standard (CES) procurement structure—first adopted in 2016—to meet the 70×30 and 2040 Zero-Emissions Targets. But while the original CES contemplated a 50% renewables target by 2030, meeting the CLCPA’s 70×30 Target will require significant enhancements to the CES structure.

Some of those enhancements include aligning currently conflicting definitions of renewable energy, evaluating the State’s load forecast to develop renewable procurement targets, creating new Renewable Energy Standard (RES) tiers, redefining the parameters of existing RES tiers, and addressing the role and obligations of load serving entities (LSEs).

Defining a Renewable Energy System

The CLCPA White Paper addresses a lingering misalignment between what the CLCPA considers “renewable energy systems” and the more expansive list of clean technologies that have been eligible under the RES component of the CES. This misalignment primarily affects biofuels, fuel cells and hydropower:

  1. Biofuels. Perhaps most controversially, biofuels were carved out of the CLCPA definition of renewable energy systems and, therefore, will not be considered an acceptable source of energy to meet the CLCPA targets. In light of this discrepancy, the CLCPA White Paper recommends the Commission realign future NYSERDA procurements to exclude biofuels.
  2. Fuel cells. While the RES considers all fuel cells to be eligible clean technology, the CLCPA only considers fuel cells to be “renewable energy” to the extent they do not utilize a fossil fuel resource in the process of generating electricity. The CLCPA White Paper recommends adopting the CLCPA limitation on fuel cells to narrow the scope of their CES eligibility. This would, for example, exclude from eligibility fuel cells that use hydrogen produced from natural gas or grid power, but allow hydrogen produced from other renewable energy resources to qualify and be eligible to generate RECs based on the attributes of the electricity used to produce the hydrogen fuel. This development could align economic incentives to promote power-to-gas systems deployed in conjunction with wind or solar farms that have excess or off-peak power, providing additional revenue streams and enhancing long-term or seasonal storage capabilities.
  3. Hydropower. Unlike the approach to biofuels and fuel cells, which had their eligibility either eliminated or narrowed by the CLCPA, hydroelectric systems were given a more expansive definition under the CLCPA than the RES. While RES Tier 1-eligible hydroelectric resources are limited to low-impact run-of-river projects and incremental production associated with certain non-storage-impoundment upgrades, the CLCPA considers all hydroelectric resources to be renewable energy systems. Nevertheless, the CLCPA White Paper recommends limiting eligibly of hydropower to the more narrow RES definition. Though, as described further below, the CLCPA White Paper proposes several other policies which could bolster the State’s hydropower sector.

70×30 Vision

In order to estimate renewable procurement requirements to meet the 70×30 Target, the CLCPA White Paper first attempts to predict Statewide electric load in 2030 in a manner that accounts for the myriad of interwoven policies, market factors and consumer behavior that will shape the next decade of the electric grid. In doing so, DPS Staff and NYSERDA assume rapid and expansive electrification of the heating and transportation sectors to the tune of an additional 10,334 and 9,048 gigawatt hours (GWh) of load, respectively, by 2030. Those electrification efforts would be offset by an estimated (but not well-defined) 40,865 GWh reduction associated with energy efficiency improvements. When netted out, the CLCPA White Paper assumes a 2030 load projection of 151,678 GWh—70% of which would be derived from renewable sources to meet the 70×30 Target. Taking into account existing and contracted renewable energy systems, and estimating future procurement needs to fill the remaining delta, the CLCPA White Paper predicts a 2030 power profile that is comprised of six primary renewable energy categories:

CA 2020 06 23 graph 1

Hydropower has long played a critical role in New York State’s power grid, though not in an evenly distributed manner. Hydropower represents approximately 41% of upstate energy production, while only 4% of downstate energy production. Collectively, that’s approximately 23% of the Statewide production portfolio. Recognizing the critical role of this resource, the CLCPA White Paper provides unwavering support for the State’s hydropower facilities, going so far as to suggest that should their financial viability and market competitiveness ever be at risk, around-market subsidies—something akin to nuclear subsidies, or “Zero-Emissions Credits (ZECs)”—could be created to bolster their bottom lines.

Modernizing the CES

Meeting the 70×30 Target will require an enormous increase in Tier 1 RES procurement. The CLCPA White Paper projects that NYSERDA will need to ramp up its procurement efforts by an additional 40% from the previous three years to secure 24,990 GWh of new renewable resources by 2026 to be operational by 2030. In order to meet those tight time frames, New York State will need to emphasize viable projects and ensure the newly passed Accelerated Renewable Energy Growth & Community Benefit Act (“Accelerate Act”) provides an efficient and streamlined review and approval process. In the previous decade, only six large-scale renewable energy projects successfully made it through the Article 10 gauntlet to receive certificates of completion. The newly created Office of Renewable Energy Siting will need to develop streamlined siting standards to course correct and set New York State on a path that unlocks investment and economic development initiatives in a timely manner. To remain on target, the CLCPA White Paper recommends the Commission adopt a multitude of changes to the CES procurement process, several of which are described below:

  1. Flexible targets. While the CLCPA White Paper projects that 4,500 GWh of new procurements per year will be needed to meet the 70×30 Target, it recommends that NYSERDA have significant flexibility to revise and adjust annual procurement targets in response to market conditions. While flexibility may provide some economic efficiencies, a lack of rigidity may dampen market and financial certainty.
  2. Emphasis on viability. The CLCPA White Paper recommends giving NYSERDA unprecedented veto power to outright reject a project that is deemed non-viable by a unanimous decision of the Technical Evaluation Panel. It also recommends merging the “project viability” and “operational flexibility and peak coincidence” metrics into one category weighted at 20% on the theory that these two metrics will become increasingly intertwined over the next decade.
  3. Interactive effects and risk factors. The CLCPA White Paper recognizes that efficient operation of a 70% renewable electric grid requires careful planning to avoid curtailment, congestion or adverse reliability impacts. It recommends tasking NYSERDA with developing new portfolio risk factors that may evaluate the geographic concentration of projects with similar generation profiles; overdependence on certain technology types; and anticipated curtailment, congestion or transmission constraints. While not addressed in the CLCPA White Paper, it remains to be seen whether and to what extent the New York Independent System Operator (NYISO) will oversee or contribute to the development of those risk factors based on its technical role as grid operator and reliability manager. NYSERDA’s risk factors would be published in a particular request for proposal to allow bidders to adjust their projects or respond appropriately to the identified concern. As markets evolve, it’s possible that developers will respond to identified risk factors with innovative market-based solutions such as co-located storage or power-to-gas to produce renewable hydrogen and/or renewable natural gas.
  4. Offshore wind. The CLCPA White Paper recommends sending a clear investment signal to the offshore wind industry by formally adopting the CLCPA target of 9 gigawatts (GW) of offshore wind by 2035 and allowing NYSERDA to procure additional Offshore Renewable Energy Credits (ORECs) to meet that goal. It also recommends development of a one million dollar feasibility study to evaluate offshore wind opportunities in the Great Lakes region, and to consider whether and to what extent Great Lakes wind projects could compete in OREC solicitations or benefit from other procurement mechanisms.
  5. New Tier 4. In recognition of New York State’s “tale of two grids”—whereby the upstate region is powered by mostly zero-emissions resources, but the downstate region is supplied by mostly fossil-fired resources—the CLCPA White Paper proposes the creation of a new Tier 4 of the CES. Tier 4 would provide financial incentives for renewable energy delivered into New York City (Zone J), separate and apart from the Offshore Wind Standard. To be eligible for Tier 4, a resource must (a) meet the CLCPA definition of renewable energy, (b) have a commercial operation date on or after the date of a Commission order resulting from the CLCPA White Paper, and (c) deliver that energy into Zone J, subject to certain additionality requirements above historical baselines. Hydropower appears to be given special treatment under the proposal such that the vintage requirements are reversed—existing hydropower appears to be eligible, but new hydropower impoundments not in existence or currently under construction would be ineligible. The CLCPA White Paper recommends that NYSERDA initially procure up to 3,000 megawatts (MW) of Tier 4 resources, with the potential to increase its solicitation with approval from the Commission. Tier 4 incentives would be funded by all LSEs based on a percentage of their Statewide load, similar to RECs and ZECs.
  6. Modifications to Tier 2. Separate and apart from the CLCPA White Paper, NYSERDA has a petition currently pending before the Commission for approval of a competitive Tier 2 program for baseline renewable resources. The CLCPA White Paper, however, seeks comments on whether NYSERDA should be authorized to resell unused Tier 2 RECs and requests further evaluation of how New York Power Authority’s (NYPA) hydroelectric resources should be treated under the Tier 2 program given NYPA’s portfolio and unique position compared to other LSEs.
  7. Modifications to Tier 1 repowered facilities. The CLCPA White Paper proposes several modifications to the circumstances under which a repowered facility may be eligible for Tier 1, setting forth a formula that incorporates the project’s useful life, the extent to which repowering includes replacement of prime mover components and the time period in which the repowering occurs. Eligible repowerings could deem an entire facility’s output as Tier 1-eligible after its initial useful life.

As CES procurement requirements are adjusted, so too are LSE obligations. The CLCPA White Paper acknowledges that LSEs will be subject to Tier 2 and Tier 4 REC procurement obligations if approved by the Commission—costs which are unknown, substantial and will, of course, be passed to customers. While the CLCPA White Paper recognizes that LSEs play a key role in supporting Statewide policy (and suggests that LSEs will pass through those costs to customers), the ability of certain LSEs—namely, Energy Service Companies (ESCOs)—to pass through CES costs, among other things, has come under increased scrutiny and could threaten the integrity of the retail marketplace.1 The CLCPA White Paper also recommends adjustments to the Tier 1 REC obligations for 2021 and 2022 to account for permitting and construction delays that have dampened quantities of available RECs. The updated Tier 1 REC obligations would be 2.04% in 2021, 5.61% in 2022, and 8.20% in 2023. If adopted, this recommendation will have ripple effects on the quantity of renewable energy that ESCOs must provide in order to offer eligible “green” electricity products as defined under the Commission’s December 12, 2019 Order Adopting Changes to the Retail Access Energy Market and Establishing Further Process.

The CLCPA White Paper is concentrated on CES procurements and therefore is, by its nature, supply-focused. Nevertheless, it provides some surface-level acknowledgement that while new renewable generation is necessary and appropriate, the State must also actively pursue technologies which improve the functionality and economics of existing clean resources and/or opportunities to repurpose existing facilities. A comprehensive pathway to the CLCPA mandates will require substantial and wide-ranging non-generation solutions if the State is to achieve a decarbonized power grid in an economic and efficient manner. Supply is only one-third of the equation. Demand reduction and delivery optimization efforts must also continue to be prioritized and incentivized so that new resources are strategically procured and located in close proximity to load to maximize efficiency and contain costs.

It is unclear what role the New York State Climate Action Council, formed to set policy and direct implementation of the CLCPA, will play relative to the refinement and implementation of the CLCPA White Paper, particularly as it was statutorily mandated to develop much of what is addressed therein. The CLCPA White Paper proposes groundbreaking reforms to New York State’s procurement strategy and provides insight into how DPS Staff and NYSERDA envision what could be the most transformational decade of New York State’s power grid. It also recognizes the “vast economic opportunity” that is presented by the CLCPA, noting that New York State has created 159,000 clean energy jobs in the last four years alone, representing a growth factor that is more than double that of the State’s overall economy.

Additional Assistance

For further assistance, please contact a member of the Energy Practice Team or the Phillips Lytle attorney with whom you have a relationship.

  1. See e.g. Case 20-E-0243, Petition of UtiliSave, LLC for a Declaratory Ruling Regarding ZEC Costs (filed May 26, 2020).